81. |
Route & Topographic survey of Access Road for S-10 wellhead for M/s. OMV (Pakistan) Exploration G.M.B.H |
2006 |
7 kM |
82. |
Topographic survey of query areas of Clay + Limestone
For M/s. Maple Leaf Cement Factory, Iskanderabad. |
2006 |
3600 Acres |
83. |
Topographic survey of Kadanwari Airstrip and adjoining area for M/s. OMV (Pakistan) Exploration G.M.B.H |
2006 |
250 Acres |
84. |
Route & Topographic survey and designing of Access Road for Latif-1 well location in Latif Block for OMV (Pakistan) Exploration G.M.B.H |
2006 |
13.2 Km |
85. |
Demarcation of Well Locations and Seismic Lines in Rhodo Block in Taunsa for Dewan Petroleum (Pvt.) Ltd |
2006 |
3 wells |
86. |
Topographic Survey of for Green Power at Dadu for M/s. Zaheeruddin Consultants (Pvt.) Ltd |
2006 |
50 Acres |
87. |
Demarcation of Residential and commercial area of Billy’s Green Towers Project for M/s. Orient Builders, Karachi |
2006 |
16 Acres |
88. |
Detailed Topographic & Physical Survey of Berth Areas from 10 to 17 at Karachi Port for M/s. Zaheeruddin Consultants (Pvt.) Ltd. |
2006 |
150 Acres |
89. |
Demarcation of Marquee area in Pearl continental Hotel & Marriot Hotel - Karachi |
2006 |
2 sites |
90. |
Physical & As-Built survey of Parking and surrounding areas of Pearl Continental Hotels, Karachi. |
2006 |
1.5 Acres |
91. |
Carrying out the survey of outfall pipeline route and Gharo Creek Nala at Port Qasim, for Pakistan PTA Ltd. |
2006 |
2.5 Km |
92. |
Topographic survey of P.D.H.A Head Office site in D.H.A phase-VIII. |
2007 |
15 Acres |
93. |
Collection of electric poles data in D.H.A Phase-VIII amd PAF Base Masroor for M/s. World Call Broadband Ltd |
2007 |
400 Acres |
94. |
Topographic survey of part area of Karachi Thermal Power Plant, Korangi. |
2007 |
25 Acres |
95. |
Topographic & demarcation survey of land at Link Road for Aga Khan (Faculty of Arts & Sciences) |
2007 |
600 Acres |
96. |
Route and Topographic survey of Trunk Lines, Flowlines Access Roads and well sites at Manzalai Oil Field Development Surface Facilities of MOL Pakistan, for VECO Engineering, Abu Dhabi. |
2007 |
50 Km |
97. |
Centerline Survey of existing Roads and Tracks in Sawan, Miano, Tajjal & Latif concessions for OMV (Pakistan) Exploration G.M.B.H |
2007 |
600 Km |
98. |
Cross Section of Stadium Road for M/s. Aga Khan University Hospital, Karachi |
2007 |
1.5 Km |
99. |
Topographic Survey of Timber Pond Area along M.A.Jinnah Road for M/s. Zaheeruddin Consultants (Pvt.) Ltd |
2007 |
150 Acres |
100 |
Reconnaissance & Topographic Survey of Latif-1 Proposed Pipeline Route for M/s. OMV (Pakistan) Exploration G.M.B.h |
2007 |
25 Km |